First Phase of Water Main Replacement Project Nears Completion

If you’ve driven down West Garfield or North Fillmore lately, you may have noticed Osceola Water Works making some big changes underground. The project, which began earlier this summer, focused on replacing the old cast iron water mains in the 200 block of West Garfield and the 600 block of North Fillmore with brand-new PVC pipe. This upgrade is a big step forward in improving the service reliability of Osceola’s water system. Looking at the project numbers, crews installed roughly 768 feet of new 6-inch water main, added two fire hydrants, six gate valves, and replaced ten service connections going